Linked modular cabins forming a 220-person site office and welfare complex on a tight urban regeneration project.
A Tier-1 contractor needed 220-person site offices and welfare on a busy construction site with very limited footprint. The complex had to include meeting rooms, drying rooms, WCs, showers, canteen and induction room.
We built a 24-cabin linked complex on two storeys, including an enclosed central plant courtyard. Cabins were drawn from our hire fleet, fitted out with furniture and IT, and craned into position over a single weekend possession. Built using established prefabrication techniques.
Read about our portable cabin hire service or browse the construction sector.
The complex was operational 18 days after the order. The site team gained a full 12 weeks of programme over a brick-built alternative and the modular structure can be relocated to the next project.